Representative Distribution Projects

Tier 1 provided engineering and design services for the development of work order packages across approximately 23 distribution feeders, supporting enhanced system reliability and operational planning.
Project Scope:
-
Installation of three-phase reclosers, tripsavers, and fault current indicators
-
Fuse removals to optimize feeder protection
Key Deliverables:
-
Pole load analysis using Pole Foreman
-
Detailed bill of materials
-
Proposed protection single-line diagrams
Key Outcomes:
-
Enhanced feeder reliability and operational efficiency
-
Delivered build-ready work packages to streamline field implementation
-
Supported long-term planning and system protection optimization
Project: Distribution Automation Program